| A road tanker is often the largest potentially isolated conductor which is brought on site and if incorrectly earthed, may pose a significant ignition risk.
When filling and emptying road tankers, both CLC/TR 50404 and NFPA77 recommend that fully interlocked static grounding systems are used (see CA09 - Earthing of a road tanker). However, in cases where an i nterlock is not possible, a self-testing clamp provides operator feedback via the built-in LED, ensuring that a low resistance connection has been made through paint or rust etc. to the metalwork of the tanker chassis.
BS5958 states that: During loading the vehicle should be earthed .... so that the resistance to earth is at all points less than 10 Ohms (7.2.1).